New Gorham Elementary School Project
Tentative Schedule
November 2007 - June 2008
I. Site Approval Track
Additional Engineering Studies for Department of Education (DOE), November-December 2007
Planning Board Workshop and Introduction, December 2007
Public Information Meeting & Straw Vote, January 2008
Formal Site Submission, January 2008
Proposed State Board of Education Approval, February 2008
II. Building Design Track
- LEED and High-Performance School Building Workshop, October 17, 2007
-
- Design Alternative Floor Plan, November 7, 2007
-
- Design Alternative Floor Plans, December 5, 2007
-
- Floor Plan Final Design, February 6, 2008
-
- Building Cost and Project Budget Review, March 5, 2008
-
- Final Design and Final Project Budget Building Committee Meeting, March 9, 2008
-
- Public Information Meeting and Straw Vote, March 26, 2008
-
- State Board of Education Approval, April 16, 2008
-
- Referendum Vote, June 10, 2008
|  |